In August, 2022, Trans Mountain recently completed installation of new pipeline and the replacement of an existing segment under the Coquihalla River. The work was done simultaneously to minimize impact to the environment and neighbours. LinkedIn/Trans Mountain

CALGARY — After more than four years of construction and at least $34 billion in costs, the Trans Mountain pipeline expansion project is nearly complete. Here’s a look at what milestones to expect in the coming weeks as the massive pipeline gets ready to start shipping Canadian oil to the West Coast:

Resolution of B.C. construction challenges: Crown corporation Trans Mountain Corp. has been dealing with construction-related challenges in the Fraser Valley between Hope and Chilliwack, where it encountered an “obstruction” when trying to pull the pipe into the horizontal hole that had been drilled for it. The setback forced the company to remove the pipe temporarily to address the issue, but Trans Mountain Corp. says it is nearing a resolution and expects to be able to re-install the pipe in that section within the next couple of weeks.

Mechanical completion: This marks the final stage of physical construction of the pipeline. Once the challenging segment of pipe has been successfully pulled back into its location, Trans Mountain will be able to complete the “final weld,” or what is formally known as mechanical completion.

Leave To Open: After construction is finished but before the pipeline can be put into service, there are several regulatory steps that must be completed. In accordance with the Canada Energy Regulator Act, companies require permission from the CER before commencing operations of a pipeline. This process is called Leave to Open and requires results from a series of inspections and safety tests. Because the Trans Mountain project has been constructed in phases, the company has been applying for Leave to Open permission in stages in order to allow flexibility during the commissioning and startup process.

Line fill: This term is used to describe the final stages of work required to prepare and ultimately fill the expanded pipeline system with more than four million barrels of oil. The process will take several weeks to complete. While line fill has not yet started on the newly constructed pipe, part of the Trans Mountain expansion project involves reactivating two older pipeline segments that had been maintained in a deactivated state. Initial line fill has already begun in B.C. on that section of the project.

In-service: This term refers to when the entire expanded pipeline system is fully operational and ready to make regular deliveries. According to a Bloomberg report, China’s Sinochem Group has purchased one of the first shipments, a 550,000-barrel cargo from Suncor Energy Inc., which will load from the Trans Mountain expansion pipeline in May-June. Trans Mountain is continuing to target an in-service date sometime in the second quarter of 2024.

Cleanup and reclamation: Once the expanded pipeline is operational, required cleanup and reclamation work will continue in the project’s construction zone.

This report by The Canadian Press was first published March 26, 2024.

The Canadian Press

  • 0072 Outlaw Buckers and Oil Kings 2024
    0072 Outlaw Buckers and Oil Kings 2024
  • 0069 Sask Oil Show 2024 banquet tickets
    0069 Sask Oil Show 2024 banquet tickets
  • 0071 Pride Upkeep 2024 Packages
    0071 Pride Upkeep 2024 Packages
  • 0070 Sask Oil Show 2024 pre-register
    0070 Sask Oil Show 2024 pre-register
  • 0068 Sask Oil Show 2024 booth
    0068 Sask Oil Show 2024 booth
  • 0067 PFM SaskWorks Payroll Investment Plan
    0067 PFM SaskWorks Payroll Investment Plan
  • 0066 WBPC Promo video 30 seconds
    0066 WBPC Promo video 30 seconds
  • 0065 Anova Resources field operator Oxbow
    0065 Anova Resources field operator Oxbow
  • 0064 Estevan OTS
    0064 Estevan OTS
  • 0063 Turnbull Excavating hiring crusher
    0063 Turnbull Excavating hiring crusher
  • 0062 TED_EPAC_Technology_30
    0062 TED_EPAC_Technology_30
  • 0061 SIMSA 2024 For Sask Buy Sask
    0061 SIMSA 2024 For Sask Buy Sask
  • 0060 Arizona Lithium Lease building
    0060 Arizona Lithium Lease building
  • 0059 Southeast College Heavy Equipment Operator
    0059 Southeast College Heavy Equipment Operator
  • 0058 Royal Helium Steveville opens anonymous rocket
    0058 Royal Helium Steveville opens anonymous rocket
  • 0055 Smart Power Be Smart with your Power office
    0055 Smart Power Be Smart with your Power office
  • 0053 Kingston Midstream Westspur Alameda Click Before You Dig large text
    0053 Kingston Midstream Westspur Alameda Click Before You Dig large text
  • 0052 Predator Inspections
    0052 Predator Inspections
  • 0051 JML Hiring Pumpjack assembly
    0051 JML Hiring Pumpjack assembly
  • 0049 Scotsburn Dental soft guitar
    0049 Scotsburn Dental soft guitar
  • 0046 City of Estevan This is Estevan
    0046 City of Estevan This is Estevan
  • 0041 DEEP Since 2018 now we are going to build
    0041 DEEP Since 2018 now we are going to build
  • 0032 IWS Summer hiring rock trailer music
  • 0022 Grimes winter hiring
  • 0021 OSY Rentals S8 Promo
  • 0018 IWS Hiring Royal Summer
  • 0015 Latus Viro
    0015 Latus Viro
  • 0013 Panther Drilling PO ad 03 top drive rigs
  • 0011
  • 0006 JK Junior
  • 0002 gilliss casing services
    0002 gilliss casing services
  • 9002 Pipeline Online 30 sec EBEX
    9002 Pipeline Online 30 sec EBEX
  • 9001

 

Conservatives blast pro-carbon price economists as ‘so-called experts’

Conservative premiers are lying about carbon pricing: Trudeau