The terminus for the Coastal GasLink natural gas pipeline is seen at the LNG Canada export terminal under construction in Kitimat, B.C., on Wednesday, September 28, 2022. THE CANADIAN PRESS/Darryl Dyck

By Amanda Stephenson in Calgary

TC Energy Corp. is expecting what it calls a “material increase” in the cost of its Coastal GasLink pipeline project.

The Calgary-based pipeline company said in an investor presentation Tuesday that it is facing significant cost pressures in Western Canada related to labour costs and shortages of skilled labour, along with contractor underperformance and disputes.

The project has also been hurt by other unexpected events including drought conditions, and erosion and sediment control challenges, the company said.

TC Energy did not put a dollar value on the cost overruns, though it said it expects to provide an updated capital cost estimate early next year that will incorporate the recent developments.

It is the second time in a handful of months that TC Energy has flagged the rising costs of Coastal GasLink. In July, the company said it expected the cost of the project spanning northern British Columbia had risen to $11.2 billion compared with an earlier estimate of $6.6 billion.

The 670-kilometre pipeline, which aims to carry natural gas across the province to the LNG Canada processing and export facility in Kitimat, B.C., is 80 per cent complete.

TC Energy CEO François Poirier said the company is pursuing potential recoveries from contractors to offset a portion of the rising costs, though those efforts might not be concluded until after the project is completed.

The company still expects Coastal GasLink to be completed by the end of 2023, and Poirier said its escalating price tag won’t keep TC Energy from achieving its debt reduction target.

“Although Phase One of Coastal GasLink has been challenged by cost performance, we do not expect any impact on the sustainability of our dividend growth rate of three to five per cent or our ability to accelerate our deleveraging target from 2026,” said Poirier in a news release.

The Coastal GasLink pipeline is not the only major energy infrastructure project in Canada to be plagued by cost overruns this year. In February, the company behind the ongoing Trans Mountain pipeline expansion project — which will increase oil transportation capacity from Alberta to the West Coast — announced the new cost of the project is an estimated $21.4 billion, up from an earlier estimate of $12.6 billion.

Trans Mountain Corp. blamed the surging cost projections for the project on the COVID-19 pandemic and the effects of the November 2021 flooding in B.C., as well as project enhancements, increased security costs, route changes to avoid culturally and environmentally sensitive areas, and scheduling pressures related to permitting processes and construction challenges in difficult terrain.

Budget overruns at both pipelines have provided fodder for environmental groups, who believe companies should be investing in green energy instead of traditional fossil fuels.

“The multi-billion-dollar cost overrun on this pipeline could have financed the largest investment in community-based renewables in Canadian history,” said Keith Stewart, senior energy strategist with Greenpeace Canada.

This report by The Canadian Press was first published Nov. 29, 2022.

Companies in this story: (TSX:TRP)

The Canadian Press

News from © The Canadian Press, 2022. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

  • 0072 Outlaw Buckers and Oil Kings 2024
    0072 Outlaw Buckers and Oil Kings 2024
  • 0069 Sask Oil Show 2024 banquet tickets
    0069 Sask Oil Show 2024 banquet tickets
  • 0071 Pride Upkeep 2024 Packages
    0071 Pride Upkeep 2024 Packages
  • 0070 Sask Oil Show 2024 pre-register
    0070 Sask Oil Show 2024 pre-register
  • 0068 Sask Oil Show 2024 booth
    0068 Sask Oil Show 2024 booth
  • 0067 PFM SaskWorks Payroll Investment Plan
    0067 PFM SaskWorks Payroll Investment Plan
  • 0066 WBPC Promo video 30 seconds
    0066 WBPC Promo video 30 seconds
  • 0065 Anova Resources field operator Oxbow
    0065 Anova Resources field operator Oxbow
  • 0064 Estevan OTS
    0064 Estevan OTS
  • 0063 Turnbull Excavating hiring crusher
    0063 Turnbull Excavating hiring crusher
  • 0062 TED_EPAC_Technology_30
    0062 TED_EPAC_Technology_30
  • 0061 SIMSA 2024 For Sask Buy Sask
    0061 SIMSA 2024 For Sask Buy Sask
  • 0060 Arizona Lithium Lease building
    0060 Arizona Lithium Lease building
  • 0059 Southeast College Heavy Equipment Operator
    0059 Southeast College Heavy Equipment Operator
  • 0058 Royal Helium Steveville opens anonymous rocket
    0058 Royal Helium Steveville opens anonymous rocket
  • 0055 Smart Power Be Smart with your Power office
    0055 Smart Power Be Smart with your Power office
  • 0053 Kingston Midstream Westspur Alameda Click Before You Dig large text
    0053 Kingston Midstream Westspur Alameda Click Before You Dig large text
  • 0052 Predator Inspections
    0052 Predator Inspections
  • 0051 JML Hiring Pumpjack assembly
    0051 JML Hiring Pumpjack assembly
  • 0049 Scotsburn Dental soft guitar
    0049 Scotsburn Dental soft guitar
  • 0046 City of Estevan This is Estevan
    0046 City of Estevan This is Estevan
  • 0041 DEEP Since 2018 now we are going to build
    0041 DEEP Since 2018 now we are going to build
  • 0032 IWS Summer hiring rock trailer music
  • 0022 Grimes winter hiring
  • 0021 OSY Rentals S8 Promo
  • 0018 IWS Hiring Royal Summer
  • 0015 Latus Viro
    0015 Latus Viro
  • 0013 Panther Drilling PO ad 03 top drive rigs
  • 0011
  • 0006 JK Junior
  • 0002 gilliss casing services
    0002 gilliss casing services
  • 9002 Pipeline Online 30 sec EBEX
    9002 Pipeline Online 30 sec EBEX
  • 9001