This is a page from the October, 2025, Saskatchewan First Energy Security Strategy and Supply Plan which outlined plans to connect our northern and southern grids. SaskPower

 

SaskPower is moving into the next phase of procurement for its project to connect Saskatchewan’s northern and southern power grids, with a Request for Supplier Qualification (RFSQ) now posted to prequalify experienced engineering, procurement and construction (EPC) contractors.

That’s according to a Nov. 17 press release.

Two companies will be shortlisted through the RFSQ to participate in an early contractor involvement (ECI) phase before the EPC contract for the project is awarded.

“The north-south interconnection will strengthen Saskatchewan’s power system and support growing electricity demand in the north,” said Jeremy Harrison, Minister Responsible for SaskPower. “This competitive procurement process is an important step toward identifying experienced contractors with the expertise and capacity needed to deliver an infrastructure project of this scale.”

A final route has not yet been selected. Environmental and routing assessments, along with engagement with Rightsholders and Indigenous communities, are underway. Local community benefits and Indigenous participation will be considered in evaluating the responses to the RFSQ.

“Bringing qualified contractors into the process early will allow us to draw on their expertise as we further develop the project’s design, schedule, cost estimates and construction approach,” said Rupen Pandya, SaskPower President & CEO. “This is a complex project, and we remain committed to meaningful and transparent engagement with Rightsholders, Indigenous communities and other stakeholders as we work to finalize a route.”

The RFSQ closes December 14, 2026, followed by evaluation and shortlisting. The ECI phase is expected to run approximately six to nine months. EPC proposals are anticipated in late 2027, with a decision on contract award targeted for spring 2028.

 

  • 137 SASPO_2874_Self_ServeCampaign
    137 SASPO_2874_Self_ServeCampaign
  • 0136 CIC - SK Energy Security Awareness
    0136 CIC - SK Energy Security Awareness
  • 0121 Ministry of Energy and Resources April 2026
    0121 Ministry of Energy and Resources April 2026
  • 0133 LC Trucking hiring Class 1A Payden
    0133 LC Trucking hiring Class 1A Payden
  • 0132 UMWA 2026
    0132 UMWA 2026
  • 0129 Turnbull drivers operators
    0129 Turnbull drivers operators
  • 0128 OSY Rentals updated
    0128 OSY Rentals updated
  • 0126 Steel_Reef_Promo_
    0126 Steel_Reef_Promo_
  • 0118 IBEW 30 sec
    0118 IBEW 30 sec
  • 0114 Prospera Bold Vision
    0114 Prospera Bold Vision
  • 0113 Miller Epic Cinematic Hollywood trailer
    0113 Miller Epic Cinematic Hollywood trailer
  • 0102 Lori Carr Coal Extended
    0102 Lori Carr Coal Extended
  • 0099 Mryglod Steel 1080p
    0099 Mryglod Steel 1080p
  • 0095 Fast Trucking nearly 70 years good at it
    0095 Fast Trucking nearly 70 years good at it
  • 0046 City of Estevan This is Estevan Teaser
    0046 City of Estevan This is Estevan Teaser
  • 0077 Caprice Resources Stand Up For Free Speech
    0077 Caprice Resources Stand Up For Free Speech
  • 0061 SIMSA 2024 For Sask Buy Sask
    0061 SIMSA 2024 For Sask Buy Sask
  • 0051 JML Hiring Pumpjack assembly
    0051 JML Hiring Pumpjack assembly
  • 0049 Scotsburn Dental soft guitar
    0049 Scotsburn Dental soft guitar
  • 0032 IWS Summer hiring rock trailer music
  • 0022 Grimes winter hiring
  • 0018 IWS Hiring Royal Summer
  • 0013 Panther Drilling PO ad 03 top drive rigs
  • 0002 gilliss casing services
    0002 gilliss casing services
  • 9002 Pipeline Online 30 sec EBEX
    9002 Pipeline Online 30 sec EBEX
  • 9001

 

 

 

Brian Zinchuk: Three Alberta natural gas power units going into mothballs. Wanna bet it’s because of zero dollar pricing?