No-till seeding near Stanraer, SK. That’s northwest of Rosetown. Can you tell there’s a pipeline under there? No? Exactly. That’s the point. Enbridge

Four years after the major work wrapped up, the last of the reseeding took place in October

The official record shows that construction of the Canadian portion of Enbridge’s Line 3 Replacement Program (L3RP) was completed more than four years ago and that the new pipeline came into commercial service in December 2019.

But as the general public marked those milestones, small Enbridge construction crews readied to tackle a final series of tasks – ensuring full and final restoration of the 1,070-km pipeline’s surface corridor to its pre-construction state.

“Most people thought we were done with Line 3 in 2019, but there’s plenty of work that goes on in the field even after construction is complete and a new pipeline becomes operational,” said Enbridge Construction Manager Allen Sawatzky. “With the last seed sown within the pipeline right-of-way (RoW) at the end of October, we can now say the job is truly complete.”

Line 3 Construction Manager Allen Sawatzky (right) and contractor Brodie Charteris checking progress along the right-of-way. Enbridge

 

Going forward, maintenance of the pipeline RoW will continue under the Enbridge Operations team.

At the time of its construction, L3RP was the largest Canadian pipeline project in more than a decade. It included installation of 36-inch-diameter, Canadian-made steel pipe over a vast stretch of the Prairies, three above-ground tanks capable of storing up to 1 million barrels of oil, and 18 pump stations to keep the product flowing. Construction took place over several seasons by a peak workforce of about 5,300.

Enbridge Line 3 Replacement map. Enbridge

 

Both during and after construction, Enbridge worked closely with landowners to identify patches of land that would require additional attention such as reseeding, noxious weed control or rearranging topsoil among other measures. Aerial and ground surveys also helped pinpoint these areas.

For the restoration crew, each morning began early with a “tailgate” safety meeting to discuss the day’s work. Enbridge

By the start of 2023, a total of 84 items remained in need of some form of additional attention. With the support of subcontractors – Castle Oilfield Construction of Virden, MB and Neil Charteris Reclamation Services Inc. of Kerrobert, SK – this final field work commenced in the spring and wrapped up in a snow-dusted field near Kerrobert on Oct. 29.

  • 0084 EMP Metals Pipeline Online
    0084 EMP Metals Pipeline Online
  • 0053 Kingston Midstream Westspur Alameda Click
    0053 Kingston Midstream Westspur Alameda Click
  • 0082 CsHM 2024 Pipeline
    0082 CsHM 2024 Pipeline
  • 0077 Caprice Resources Stand Up For Free Speech
    0077 Caprice Resources Stand Up For Free Speech
  • 0076 Latus only
    0076 Latus only
  • 0061 SIMSA 2024 For Sask Buy Sask
    0061 SIMSA 2024 For Sask Buy Sask
  • 0055 Smart Power Be Smart with your Power office
    0055 Smart Power Be Smart with your Power office
  • 0051 JML Hiring Pumpjack assembly
    0051 JML Hiring Pumpjack assembly
  • 0049 Scotsburn Dental soft guitar
    0049 Scotsburn Dental soft guitar
  • 0046 City of Estevan This is Estevan
    0046 City of Estevan This is Estevan
  • 0041 DEEP Since 2018 now we are going to build
    0041 DEEP Since 2018 now we are going to build
  • 0032 IWS Summer hiring rock trailer music
  • 0022 Grimes winter hiring
  • 0021 OSY Rentals S8 Promo
  • 0018 IWS Hiring Royal Summer
  • 0013 Panther Drilling PO ad 03 top drive rigs
  • 0011
  • 0006 JK Junior
  • 0002 gilliss casing services
    0002 gilliss casing services
  • 9002 Pipeline Online 30 sec EBEX
    9002 Pipeline Online 30 sec EBEX
  • 9001

 

The full scope of work in 2023 involved:

  • Reseeding pasture seed mixes following a third year of drought and poor germination in parts of Alberta and Saskatchewan;
  • No-till drilling and hydro seed (applied wet with tackifier seed mix) to stick to steep, dry slopes;
  • Rearranging topsoil and repairing settled ditch lines;
  • Side-by-side chemical boom spraying, select hand spraying and mowing to control weeds; and,
  • Tractor, skid steer and whipper snipper hand mowing.

“From the very beginning, Enbridge made a commitment that we would leave the land in as good or in better condition than it was before construction started,” Sawatzky said, “and we can now say we’ve done what we said we would do and made good on that promise.”

2. In some areas, seed was applied wet, with a tackifier to adhere to dry slopes. Enbridge

The construction manager’s words are borne out by a total of 61 formal field inspections conducted by the Canada Energy Regulator (CER) dating to September 2017. While the focus of these inspections was environmental protection and reclamation, they also touched on erosion and sediment control, sites of Indigenous significance and general environmental compliance.

In keeping with commitments to landowners and Indigenous communities, the restoration crew also featured a monitor from the Canadian Association of Energy Pipeline & Landowner Associations (CAEPLA) as well as an Indigenous construction liaison.

“At the end of the day, the people who live along or in proximity to the pipeline right-of-way are Enbridge’s neighbours and we have an obligation to continuously live up to the trust that they’ve placed in us,” Sawatzky concluded. “That’s really what drives us.”

 

  • 0084 EMP Metals Pipeline Online
    0084 EMP Metals Pipeline Online
  • 0053 Kingston Midstream Westspur Alameda Click
    0053 Kingston Midstream Westspur Alameda Click
  • 0082 CsHM 2024 Pipeline
    0082 CsHM 2024 Pipeline
  • 0077 Caprice Resources Stand Up For Free Speech
    0077 Caprice Resources Stand Up For Free Speech
  • 0076 Latus only
    0076 Latus only
  • 0061 SIMSA 2024 For Sask Buy Sask
    0061 SIMSA 2024 For Sask Buy Sask
  • 0055 Smart Power Be Smart with your Power office
    0055 Smart Power Be Smart with your Power office
  • 0051 JML Hiring Pumpjack assembly
    0051 JML Hiring Pumpjack assembly
  • 0049 Scotsburn Dental soft guitar
    0049 Scotsburn Dental soft guitar
  • 0046 City of Estevan This is Estevan
    0046 City of Estevan This is Estevan
  • 0041 DEEP Since 2018 now we are going to build
    0041 DEEP Since 2018 now we are going to build
  • 0032 IWS Summer hiring rock trailer music
  • 0022 Grimes winter hiring
  • 0021 OSY Rentals S8 Promo
  • 0018 IWS Hiring Royal Summer
  • 0013 Panther Drilling PO ad 03 top drive rigs
  • 0011
  • 0006 JK Junior
  • 0002 gilliss casing services
    0002 gilliss casing services
  • 9002 Pipeline Online 30 sec EBEX
    9002 Pipeline Online 30 sec EBEX
  • 9001