FILE – An above-ground section of Enbridge’s Line 5 at the Mackinaw City, Mich., pump station sits on Oct. 7, 2016. A federal judge on Friday, June 16, 2023, ordered energy company Enbridge to shut down within three years parts of the oil pipeline that traverses the northern Wisconsin territory of a Native American tribe and to pay the tribe more than $5 million for trespassing on its property. (AP Photo/John Flesher, File)

MADISON, Wis. (AP) — A federal judge has given Enbridge three years to shut down parts of an oil pipeline that crosses reservation land and ordered the energy company to pay a Native American tribe more than $5 million for trespassing.

Friday’s order from U.S. District Judge William Conley came after members of the Bad River Band of Lake Superior Chippewa told him during a hearing in Madison that the Enbrige Line 5 pipeline is at immediate risk of being exposed by erosion and rupturing on their land.

The tribe argued that an emergency exists because large sections of nearby riverbank have washed away this year, leaving less than 15 feet (4.6 meters) of land between Line 5 and the Bad River as it meanders on the reservation.

Experts and environmental advocates have warned in court that exposed pipelines would be weakened and could rupture at any time, causing massive oil spills.

The judge’s order said a rupture on tribal land “would unquestionably be a public nuisance” but denied that the threat is imminent, and said a shutdown would likely “spark at least temporary shortages and increased prices for refined gas, propane and butane in the Upper Midwest and Eastern Canada, creating hardships, specially for the poor and other economically challenged households.”

“Nevertheless, given the environmental risks, the court will order Enbridge to adopt a more conservative shutdown and purge plan,” Conley wrote.

His order gives Enbridge three years to “cease operation of Line 5 on any parcel within the Band’s tribal territory on which defendants lack a valid right of way and to arrange reasonable remediation at those sites.”

Conley also ordered Enbridge to pay more than $5.15 million for trespassing, and to keep paying the tribe a portion of its profits for as long as the pipeline continues operating on tribal land.

Enbridge said Saturday that it plans to appeal and “remains open to an amicable resolution with the Bad River Band.” The statement says it disagrees that Enbridge is trespassing and with the judge’s order that Line 5 must stop operating on reservation land within three years.

Enbridge said the long-term solution to the dispute will be a 41-mile (66-kilometer) reroute of the pipeline, but “the project hinges on timely government permit approvals to allow construction to be completed within the next three years.”

Line 5 transports up to 23 million gallons (about 87 million liters) of oil and liquid natural gas each day, stretching 645 miles (1,038 kilometers) from the city of Superior, Wisconsin through northern Wisconsin and Michigan to Sarnia, Ontario.

The Bad River tribe sued Enbridge in 2019 to force the company to remove the roughly 12-mile (19-kilometer) section crossing its reservation, saying the 70-year-old pipeline is dangerous and that land agreements allowing Enbridge to operate on the reservation expired in 2013.

Conley sided with the tribe in September, saying that Enbridge was trespassing and must compensate the tribe for illegally using its land.

In November, Conley told Enbridge and tribal leaders to create an emergency shutoff plan given the significant risk of “catastrophic” damage to the reservation and its water supply.

The tribe’s office in Odanah, Wisconsin, was closed Saturday and a telephone message seeking comment on the order was not immediately returned.

News from © The Canadian Press, 2023. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

  • 0079 Ministry of Energy Business_incentive PO
    0079 Ministry of Energy Business_incentive PO
  • 0078 LHOS 2024
    0078 LHOS 2024
  • 0077 Caprice Resources Stand Up For Free Speech
    0077 Caprice Resources Stand Up For Free Speech
  • 0053 Kingston Midstream Westspur Alameda
    0053 Kingston Midstream Westspur Alameda
  • 0076 Latus only
    0076 Latus only
  • 0073 SaskWorks-Pipeline Online
    0073 SaskWorks-Pipeline Online
  • 0063 Turnbull Excavating hiring crusher
    0063 Turnbull Excavating hiring crusher
  • 0061 SIMSA 2024 For Sask Buy Sask
    0061 SIMSA 2024 For Sask Buy Sask
  • 0058 Royal Helium Steveville opens anonymous rocket
    0058 Royal Helium Steveville opens anonymous rocket
  • 0055 Smart Power Be Smart with your Power office
    0055 Smart Power Be Smart with your Power office
  • 0051 JML Hiring Pumpjack assembly
    0051 JML Hiring Pumpjack assembly
  • 0049 Scotsburn Dental soft guitar
    0049 Scotsburn Dental soft guitar
  • 0046 City of Estevan This is Estevan
    0046 City of Estevan This is Estevan
  • 0041 DEEP Since 2018 now we are going to build
    0041 DEEP Since 2018 now we are going to build
  • 0032 IWS Summer hiring rock trailer music
  • 0022 Grimes winter hiring
  • 0021 OSY Rentals S8 Promo
  • 0018 IWS Hiring Royal Summer
  • 0013 Panther Drilling PO ad 03 top drive rigs
  • 0011
  • 0006 JK Junior
  • 0002 gilliss casing services
    0002 gilliss casing services
  • 9002 Pipeline Online 30 sec EBEX
    9002 Pipeline Online 30 sec EBEX
  • 9001