Brian Zinchuk is editor and owner of Pipeline Online
Newfoundland and Labrador’s Muskrat Falls hydroelectric project is considered commissioned after years of delays and billions of dollars in cost overruns.
Jennifer Williams, CEO of Newfoundland and Labrador Hydro, made the announcement Wednesday to reporters in St. John’s following a weekend of successful final testing. The project, she said, will be declared officially commissioned in the near future after paperwork is completed with the federal government.
Williams said the project passed the final round of high-power testing over the weekend on the 1,100-kilometre Labrador-Island Link. That transmission system runs from the Muskrat Falls site in Labrador to a converter station outside St. John’s.
“It’s a huge moment and I know the whole province has been waiting for it for quite some time,” Williams said. “I literally was crying … this weekend when this (testing) was all happening.”
Muskrat Falls was officially approved in 2012 with an initial price tag of around $7.4 billion, which has ballooned to more than $13 billion.
The Crown utility said in a news release on Saturday that it had completed its second 700-megawatt high-power pole test, adding that it was pleased with the link’s performance. The high-power testing is meant to determine if the link can smoothly deliver high volumes of power to the province’s grid.
A previous round of high-power tests using 700 megawatts failed last November, leaving about 58,000 people in the dark for up to 25 minutes. The utility said last month that the software problem behind that failure had been fixed.
Williams said the final cost of the project would be determined in the next few months.
“We now have to finish our (power) rate-mitigation plan with the provincial government and that will take us another few months,” she said. “There will be more to say on how the rates will evolve over time.”
The utility’s next general rate application, which will include the cost of Muskrat Falls power, won’t be made with the provincial regulator until sometime next year, Williams said.
This report by The Canadian Press was first published April 12, 2023.
- 0084 EMP Metals Pipeline Online0084 EMP Metals Pipeline Online
- 0053 Kingston Midstream Westspur Alameda Click0053 Kingston Midstream Westspur Alameda Click
- 0082 CsHM 2024 Pipeline0082 CsHM 2024 Pipeline
- 0077 Caprice Resources Stand Up For Free Speech0077 Caprice Resources Stand Up For Free Speech
- 0076 Latus only0076 Latus only
- 0061 SIMSA 2024 For Sask Buy Sask0061 SIMSA 2024 For Sask Buy Sask
- 0055 Smart Power Be Smart with your Power office0055 Smart Power Be Smart with your Power office
- 0051 JML Hiring Pumpjack assembly0051 JML Hiring Pumpjack assembly
- 0049 Scotsburn Dental soft guitar0049 Scotsburn Dental soft guitar
- 0046 City of Estevan This is Estevan0046 City of Estevan This is Estevan
- 0041 DEEP Since 2018 now we are going to build0041 DEEP Since 2018 now we are going to build
- 0032 IWS Summer hiring rock trailer music
- 0022 Grimes winter hiring
- 0021 OSY Rentals S8 Promo
- 0018 IWS Hiring Royal Summer
- 0013 Panther Drilling PO ad 03 top drive rigs
- 0011
- 0006 JK Junior
- 0002 gilliss casing services0002 gilliss casing services
- 9002 Pipeline Online 30 sec EBEX9002 Pipeline Online 30 sec EBEX
- 9001