Enbridge Line 5. Map courtesy Enbridge

WASHINGTON — A Wisconsin judge has ruled in favour of an Indigenous band in its dispute with Enbridge over Line 5, but stopped short of shutting down the controversial cross-border pipeline.

District Court Judge William Conley says the Bad River Band of the Lake Superior Chippewa has proven it was entitled to revoke permission for the pipeline to cross its territory back in 2013.

Conley also says the band, which wants the line removed from the Bad River reservation, is entitled to financial compensation — although the decision does not go into detail on that front.

The judge rejected the band’s motion to have the pipeline shut down, however, citing the potential for serious foreign policy and trade consequences for both Canada and the United States.

He acknowledges Foreign Affairs Minister Mélanie Joly’s decision late last month to formally invoke a 1977 treaty between the two countries that specifically covers cross-border pipelines.

Conley’s order, issued late Wednesday, also requires Enbridge to reroute the pipeline around Bad River territory within five years, an effort the company says is already underway.

“The court will grant the band’s motion with respect to its trespass and unjust enrichment claims, Enbridge’s counterclaims and the band’s entitlement to a monetary remedy,” he writes.

“Nevertheless, the court must deny the band’s request for an automatic injunction, as an immediate shutdown of the pipeline would have significant public and foreign policy implications.”

Environmental concerns are top of mind in Wisconsin, where the pipeline runs directly through the Bad River Reservation, more than 500 square kilometres of pristine wetlands, streams and wilderness.

The band has been in court with Enbridge for more than three years, arguing that the Calgary-based company is trespassing, having violated the terms of the easements that allowed the pipeline to traverse the reservation beginning in 1953.

Enbridge, which is in the process of trying to reroute the pipeline around the reservation, argued that a 1992 agreement with the Bad River Band allows the pipeline to keep operating until 2043.

Conley, however, concluded that the band was within its rights to decide not to renew the easements in 2013, and that the 1992 agreement was not by itself a guarantee that the pipeline would be allowed to continue to operate.

“The agreed-upon purpose was not, as Enbridge now asserts, to permit it to operate across the entire reservation for 50 years,” the judge writes.

“Moreover, Enbridge knew of the risk that its 20-year easements … might not be renewed, and yet failed to protect itself from that risk.”

Line 5 has been under legal siege in both Wisconsin and neighbouring Michigan for the better part of the last three years, and with opponents in both cases arguing for a shutdown, the ruling Wednesday is likely to be seen as a win.

Business groups and chambers of commerce on both sides of the border, provincial governments and Ottawa have rallied behind Enbridge in its effort to portray Line 5’s survival as a mission-critical matter of continental energy security.

Allies have argued, both in court filings as well as public forums, that Line 5 is a vital source of energy for several Midwestern states, and an essential link for Canadian refineries that fuel some of Canada’s busiest airports.

Late last month, the company won a key battle in the suit in Michigan, where a federal judge rejected Attorney General Dana Nessel’s efforts to get the case removed back to circuit court, where the state stands a better chance of success.

Nessel has since indicated she plans to appeal that decision.

This report by The Canadian Press was first published Sept. 8, 2022.

Companies in this story: (TSX:ENB)

James McCarten, The Canadian Press

News from © The Canadian Press, 2022. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

  • 0072 Outlaw Buckers and Oil Kings 2024
    0072 Outlaw Buckers and Oil Kings 2024
  • 0069 Sask Oil Show 2024 banquet tickets
    0069 Sask Oil Show 2024 banquet tickets
  • 0071 Pride Upkeep 2024 Packages
    0071 Pride Upkeep 2024 Packages
  • 0070 Sask Oil Show 2024 pre-register
    0070 Sask Oil Show 2024 pre-register
  • 0068 Sask Oil Show 2024 booth
    0068 Sask Oil Show 2024 booth
  • 0067 PFM SaskWorks Payroll Investment Plan
    0067 PFM SaskWorks Payroll Investment Plan
  • 0066 WBPC Promo video 30 seconds
    0066 WBPC Promo video 30 seconds
  • 0065 Anova Resources field operator Oxbow
    0065 Anova Resources field operator Oxbow
  • 0064 Estevan OTS
    0064 Estevan OTS
  • 0063 Turnbull Excavating hiring crusher
    0063 Turnbull Excavating hiring crusher
  • 0062 TED_EPAC_Technology_30
    0062 TED_EPAC_Technology_30
  • 0061 SIMSA 2024 For Sask Buy Sask
    0061 SIMSA 2024 For Sask Buy Sask
  • 0060 Arizona Lithium Lease building
    0060 Arizona Lithium Lease building
  • 0059 Southeast College Heavy Equipment Operator
    0059 Southeast College Heavy Equipment Operator
  • 0058 Royal Helium Steveville opens anonymous rocket
    0058 Royal Helium Steveville opens anonymous rocket
  • 0055 Smart Power Be Smart with your Power office
    0055 Smart Power Be Smart with your Power office
  • 0053 Kingston Midstream Westspur Alameda Click Before You Dig large text
    0053 Kingston Midstream Westspur Alameda Click Before You Dig large text
  • 0052 Predator Inspections
    0052 Predator Inspections
  • 0051 JML Hiring Pumpjack assembly
    0051 JML Hiring Pumpjack assembly
  • 0049 Scotsburn Dental soft guitar
    0049 Scotsburn Dental soft guitar
  • 0046 City of Estevan This is Estevan
    0046 City of Estevan This is Estevan
  • 0041 DEEP Since 2018 now we are going to build
    0041 DEEP Since 2018 now we are going to build
  • 0032 IWS Summer hiring rock trailer music
  • 0022 Grimes winter hiring
  • 0021 OSY Rentals S8 Promo
  • 0018 IWS Hiring Royal Summer
  • 0015 Latus Viro
    0015 Latus Viro
  • 0013 Panther Drilling PO ad 03 top drive rigs
  • 0011
  • 0006 JK Junior
  • 0002 gilliss casing services
    0002 gilliss casing services
  • 9002 Pipeline Online 30 sec EBEX
    9002 Pipeline Online 30 sec EBEX
  • 9001

 

Michigan signals intent to appeal decision keeping Line 5 dispute in federal court

Judge sides with Enbridge Inc. in Michigan’s latest effort to halt Line 5 pipeline

Michigan wants ‘to have its cake and eat it too’ on Line 5: chambers of commerce