A major Alberta utility has cancelled a large wind power project in response to new government rules on where such developments can be built.
TransAlta CEO John Kousinioris said Friday the 300-megawatt Riplinger project near Cardston in southern Alberta will no longer proceed.
“We’ve reassessed our growth plans in the province,” he said in a conference call to analysts.
“(The project) has been impacted by the new restrictions on development near protected areas and pristine viewscapes and will not be advanced. The project has been removed from our growth pipeline.”
TransAlta is also to put three other developments on hold, as the government goes through a redesign of the province’s electricity market.
The 100-megawatt Tempest wind project south of Lethbridge is affected by that delay, as is the gas-fired, 44-megawatt Pinnacle generator west of Edmonton and the 180-megawatt WaterCharger battery storage facility near Cochrane.
- 0084 EMP Metals Pipeline Online0084 EMP Metals Pipeline Online
- 0053 Kingston Midstream Westspur Alameda Click0053 Kingston Midstream Westspur Alameda Click
- 0082 CsHM 2024 Pipeline0082 CsHM 2024 Pipeline
- 0077 Caprice Resources Stand Up For Free Speech0077 Caprice Resources Stand Up For Free Speech
- 0076 Latus only0076 Latus only
- 0061 SIMSA 2024 For Sask Buy Sask0061 SIMSA 2024 For Sask Buy Sask
- 0055 Smart Power Be Smart with your Power office0055 Smart Power Be Smart with your Power office
- 0051 JML Hiring Pumpjack assembly0051 JML Hiring Pumpjack assembly
- 0049 Scotsburn Dental soft guitar0049 Scotsburn Dental soft guitar
- 0046 City of Estevan This is Estevan0046 City of Estevan This is Estevan
- 0041 DEEP Since 2018 now we are going to build0041 DEEP Since 2018 now we are going to build
- 0032 IWS Summer hiring rock trailer music
- 0022 Grimes winter hiring
- 0021 OSY Rentals S8 Promo
- 0018 IWS Hiring Royal Summer
- 0013 Panther Drilling PO ad 03 top drive rigs
- 0011
- 0006 JK Junior
- 0002 gilliss casing services0002 gilliss casing services
- 9002 Pipeline Online 30 sec EBEX9002 Pipeline Online 30 sec EBEX
- 9001
“They have been placed on hold until we receive sufficient clarity,” Kousinioris said.
In February, the United Conservative Party government announced new rules on the development of renewable power in the province. They impose a new 35-kilometre buffer zone around protected areas and what the government calls “pristine viewscapes.”
Riplinger would have been about 45 kilometres by road from Waterton National Park and about 55 kilometres from Beauvais Lake Provincial Park.
Kousinioris said the Riplinger project would have been on the edge of an exclusion zone.
The rules followed a seven-month moratorium on renewable energy approvals after the government decided the industry was growing too quickly, threatening agriculture and marring Alberta’s landscape.
Analysts disputed the need for those restrictions, saying renewable energy is well down on the list of threats to farmland.
It’s the second setback this week for low-carbon energy generation in Alberta.
Electricity generator Capital Power announced Wednesday, May 1, it would cancel plans for a $2.4-billion carbon capture and storage project for its natural gas facility near Edmonton.
CEO Avik Dey said the cost of the project was too high and the regulatory environment around it too uncertain to justify going ahead.
This report by The Canadian Press was first published May 3, 2024.
- 0084 EMP Metals Pipeline Online0084 EMP Metals Pipeline Online
- 0053 Kingston Midstream Westspur Alameda Click0053 Kingston Midstream Westspur Alameda Click
- 0082 CsHM 2024 Pipeline0082 CsHM 2024 Pipeline
- 0077 Caprice Resources Stand Up For Free Speech0077 Caprice Resources Stand Up For Free Speech
- 0076 Latus only0076 Latus only
- 0061 SIMSA 2024 For Sask Buy Sask0061 SIMSA 2024 For Sask Buy Sask
- 0055 Smart Power Be Smart with your Power office0055 Smart Power Be Smart with your Power office
- 0051 JML Hiring Pumpjack assembly0051 JML Hiring Pumpjack assembly
- 0049 Scotsburn Dental soft guitar0049 Scotsburn Dental soft guitar
- 0046 City of Estevan This is Estevan0046 City of Estevan This is Estevan
- 0041 DEEP Since 2018 now we are going to build0041 DEEP Since 2018 now we are going to build
- 0032 IWS Summer hiring rock trailer music
- 0022 Grimes winter hiring
- 0021 OSY Rentals S8 Promo
- 0018 IWS Hiring Royal Summer
- 0013 Panther Drilling PO ad 03 top drive rigs
- 0011
- 0006 JK Junior
- 0002 gilliss casing services0002 gilliss casing services
- 9002 Pipeline Online 30 sec EBEX9002 Pipeline Online 30 sec EBEX
- 9001